New Studio nearing completion!

I had every intention of keeping you up to date on progress but the progress took so much time there wasn’t any to spare. Sorry! Well, today we emptied three B&Qs of carpet tiles – and we had to change plans half way through due to a shortage and settled on two colours instead of one.

Having returned from the Maidstone 3-day workshop on Monday, tomorrow the final work begins in earnest. It has to! We’re holding our first 2-day workshop here on September 17/18. Incidentally, it’s fully booked, so we’re running another two weeks later on October 1/2, and even that’s filling – just six places currently available.

OK, back to the studio…

The walls and ceiling are lined with plywood. I would have preferred plasterboard but the builder persuaded me that the wooden building would move and plywood would be a better choice. I’m still not convinced – especially after hours of filling and levelling all the joints. They’ll never be perfect but at least they look a lot flatter.

That job done, the paper hanging began with heavy weight liner paper. Now, I hate papering ceilings – and this one is 20′ by 22′! There’s nothing more likely to frustrate than trying to handle a 22 foot long piece of gooey paper above your head and paste it accurately.

I actually enjoy hanging paper – vertical paper! – and it took only three days to complete the four walls. By then I also had the skirting boards and architraves in place and gloss painted.

So, what are the two donkeys doing in the centre of the room? An extra and unexpected job 🙂 Jenny was raising funds for “Walk with Donkeys” in Crete and needed a collection box. The two donkeys have now been completed and fixed either side of a central box.

Donkey Charity Collection Box

Back in the studio, the ceiling received three coats of paint and I was ably assisted by my good friend Chris Howlett, who had come up from Cambridge to help. While staying in US hotels I had noticed the wall coverings and set out to find the same in the UK. If they’re good enough to take the punishment meted out in hotel rooms, I knew they’d suit me too. I finally found a source of commercial vinyl “extra scrubbable” wallpaper in a warm off-white – and 56″ wide! That really speeded the job up… until disaster struck!

The wallpaper paste soaked through the lining paper and “blew” the plaster that was smoothing the bad joint between two of the wall boards – where it mattered on the main wall I’ve earmarked for filming DVDs. We tried a couple of fixes but eventually realised that only complete renewal would suffice.

Eventually, I managed to turn back the edge of the vinyl paper, removed a section of lining paper, and re-plastered the entire joint. Finally, I succeeded in inlaying a new section of lining paper and left it for two days to dry throughly. With a lot of trepidation I set about hanging the next section of wide vinyl, knowing that I only had an inch of overlap to trim to a accurate joint. I should have mentioned that this commercial paper is not butt jointed, instead it has two selvedge and you overlap adjacent sheets by 2″. Then you cut through both sheets with a knife and smooth the cut edges together. It can (honestly!) give an almost undetectable join – when it’s done by a professional 🙂 Fortunately, the joint went well and the last wall was quickly completed.

As if I didn’t have enough to do, Pete Hogg arrived to begin work on the nearby toilet, which is good – except that I have the door frame and door to fit and install all the electrics. And all Pete has to do is convert a 100+ year-old former earth closet into a state-of-the-art restroom! He’s doing an absolutely splendid job and, as I write, should have installed the hand basin and water heater, and completed the floor tiling, tomorrow.

Pete Hogg happily working on the 'luxury restroom'

In the meantime, I’ve completed the electrics and installed the lighting. And I’m furiously completing the plan chest work table, painting the print rack, dresser and associated shelves, and this morning I installed the outdoor half of the HVAC air conditioning system. The chairs have been delivered, we have one table and will order the remainder on Monday, and… it looks as though we will be ready for the inaugural workshop 🙂

Tomorrow I’ll begin work on the interior half of the air conditioning, in between adding coats of paint to the furniture. More updates as soon as I have time… if any can be found!

Leave a Reply